Liberty Landing Update 9/8/2026

Liberty Landing Timeline:

Here is a list of the construction activities and their timelines:

• Remaining Front Street concrete pavement: 8/24 – 9/4

• Site Electrical (admin building parking lot and marina):

Finish 10/15

• Decorative Paver Plaza 8/31 – 9/9

• Metal Railing 8/31 – 9/14

• Landscaping 8/31 – 9/9

• New Richmond Sign Install 9/15

• Boat Dock Electric 9/7 – 9/19

• Boat Dock Parking Lot 9/21 -10/2

• Front/Walnut/Union/Susanna Way Final Paving 10/5 -10/8

• Pavement Striping 10/9

• Site Clean up 10/12 – 10/16

• Punchlist/Furniture 10/19 – 10/23

• Site Demobilization 10/26 – 10/30