Liberty Landing Update

Sheet pile driving is completed on the river side retaining wall 

The start of drilling and installing the tie-back anchor and hold-down anchors for the retaining wall.

Prus will start forming and pouring the retaining wall concrete cap.

In the coming week/s, the underground electric installation will begin as well as the water supply piping.