Liberty Landing Update 9/8/2026

Liberty Landing Timeline: Here is a list of the construction activities and their timelines: • Remaining Front Street concrete pavement: 8/24 – 9/4 • Site Electrical (admin building parking lot

Read More »

Liberty Landing Update

North Sidewalk from New Richmond Distillery to Walnut is currently being replaced. Construction duration for this is estimated to be completed by 6/5. From there we will proceed with removing

Read More »

Liberty Landing Update 5/27//2026

North Sidewalk from New Richmond Distillery to Walnut is currently being replaced. Construction duration for this is estimated to be completed by 6/5. From there we will proceed with removing

Read More »

Liberty Landing Update

Liberty Landing Update: They will be pouring concrete on the river side and continuing site utilities. Access will still be limited on front street.

Read More »

Liberty Landing Update 4/15/2026

The structural components of the new river wall are now complete. We are preparing to start pouring the new concrete sidewalks and concurrently working on the site electric, storm sewer,

Read More »

Liberty Landing Update 3-24-2026

Last week at Liberty Landing, the sheet pile wall was finished as the drilled drain system was completed. The concrete waler was poured and wrecked, and site utilities commenced. This

Read More »